Subject: 20621/ChgOrd2/81A/Cash/RedBankInterceptor Date: Fri, 22 Oct 1993 09:04:00 -0500 RESOLUTION NO. 20621 A RESOLUTION AUTHORIZING CHANGE ORDER NO. 2 (FINAL), CONTRACT NO. 81-A, RED BANK INTERCEPTOR CONNECTOR SEWER, WITH CASH CONSTRUCTION COMPANY, WHICH CHANGE ORDER DECREASES THE CONTRACT AMOUNT BY ONE HUNDRED SEVENTEEN THOUSAND, SEVENTY-FIVE AND 56/100 DOLLARS ($117,075.56) FOR A REVISED TOTAL CONTRACT AMOUNT OF ONE MILLION, EIGHTY-ONE THOUSAND, SEVEN HUNDRED FIFTY-SEVEN AND 04/100 DOLLARS ($1,081,757.04), AND WHICH INCREASES THE CONTRACT TIME BY ONE HUNDRED THREE (103) DAYS FOR A FINAL COMPLETION DATE OF APRIL 18, 1995. BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF CHATTANOOGA, TENNESSEE, That there be and is hereby authorized Change Order No. 2 (Final), Contract No. 81-A, Red Bank Interceptor Connector Sewer, with Cash Construction Company, which change order decreases the contract amount by $117,075.56 for a revised total contract amount of $1,081,757.04, and which increases the contract time by 103 days for a final completion date of April 18, 1995. ADOPTED: May 23, 1995 :cjc